Anaconda Copper Mine Superfund Cleanup

About the Anaconda Copper Mine

The Anaconda mine is an abandoned copper mine covering more than 3,400 acres in Yerington, Nevada, where acid run-off and waste rock containing low levels of uranium, thorium, and other exposed metals were disposed in unlined ponds. As early as the late 1970s and early 1980s, NDEP began its mediation efforts on the site. In November 2009 the U.S. EPA revealed clear evidence that the mine has contaminated the groundwater creating a toxic “plume” including uranium (3-4 times EPA standards) and arsenic (up to 50 times EPA standards) that is approaching residential and agricultural areas..Thus, the mine is a threat to the people of Yerington and the Yerington Paiute Tribe. The three primary risks are from groundwater contamination, blowing dust, and ongoing toxic drainage from the mine site facilities. Both residents and agricultural operators downgradient of the mine are at risk. In order for the contamination to be alleviated and prevent serious impacts to the community the site must be cleaned up.

Current Issues

Proposed Sale of Federally Managed Anaconda Mine site lands

Upcoming Decision of Groundwater Cleanup

Aerial view of the mine (circa 2015). Town of Yerington is in the foreground. The mining pit lake in the center has a volume of about 40,000 acre-feet.

Arimetco, (Arizona Metals Company) purchased the mine property in 1989 and proceeded with heap acid leaching and processing operations. However, only to file for bankruptcy protection in 1997, and ultimately abandoning the site in January 2000 with only $3.5 million dollar bond in the hands of the state of Nevada. Left behind were four operational heap leach pads with approximately 90 million gallons of pregnant leach solution still in the system.

The state of Nevada implemented emergency management procedures, and EPA requested that the site be placed on the National Priorities list for public funding for cleanup. But, Nevada declined EPA’s offer only to request a few years later in 2004 due to the complexity of contaminants at the site, such as radioactive contamination, that EPA step in to assume the lead regulatory agency of the site. EPA agreed using its authority under CERCLA Section 106 (Superfund); however, the site was not placed on the National Priority List (NPL). Thus, EPA was limited to conducting “removal actions,” to stabilize immediate threats at the site, which are restricted to a 12 month duration or $2 million in expenditures. Atlantic Richfield Company (ARCO, which is a subsidiary of British Petroleum) is the primary responsible party for the site and a majority of the site’s cleanup. So far, cleanup activities have been limited to emergency actions that needed to be taken to mitigate releases immediately hazardous to human health or the environment.

In 2018 the state of Nevada assumed a lead agency role from the US EPA . GBRW remains concerned that under state administration that the BP/ARC process will not be as complete a cleanup as would occur under EPA. The state of Nevada is approaching a decision in the next two years about how to address the groundwater contamination at the mine site, which is a threat to the people of Yerington and the Yerington Paiute Tribe. It is critical that there be a thorough independent publicly transparent assessment of the contamination at the site and that the most environmentally sound and socially just plan is advanced for cleanup. The recent groundwater reassessment BP/ARC conducted deviates from the assessment under EPA by reducing the scope of mining related contamination and company liability. We intend to insure that public pressure be put on the state of Nevada in its oversight role so that BP/ARC will be held accountable for the full cleanup including the goal of aquifer restoration as required by federal law under CERCLA.

Anaconda Mine Chronology

1907 Empire-Nevada Copper Mining and Smelting Company discover Yerington deposit and operates at Yerington Site from 1918 to 1920.

1941 Anaconda Mining Company acquired the property.

1951 Weed Heights housing community constructed.

1952  The Process Areas and Acid Plant constructed at the Yerington Mine Site.

1952  Mining activities began with stripping of overburden.

1953  First copper oxide ore delivered to the leaching plant.

1961 Concentrator for processing sulfide ore and sulfide tailings dam constructed.

1965 Dump leaching of low-grade copper oxide ore in the W-3 Waste Rock dump began. 1967 Sulfide ore concentrator expanded to double capacity.

1973 Nevada Bureau of Mines and Geology reported on radioactivity at Site (Bulletin 81).

1976 U.S. Geological Survey (USGS) performed a study (report published in 1982) to investigate possible groundwater impact of tailings and brine disposal at the Anaconda Copper Mine Site.

1976  Kilborn/NUS Inc. issued a report to Wyoming Mineral Corporation evaluating the feasibility of a proposed uranium processing facility at the Yerington Site.

1977  ARC purchased Anaconda Minerals, including the Site.

1978  ARC shut down all mining and processing operations.

1979  Unison leased building space in the Process Areas for the purpose of dismantling transformers for disposal.

1979 Anaconda Copper Mine was entered into the Comprehensive Environmental Response, Compensation, and Liability Information System (CERCLIS) database.

1982 The Nevada Division of Environmental Protection (NDEP) issued a Finding of Violation (FOV) to ARC for alleged ““unauthorized discharge of pollutants to waters of the state.””

1982  Site, including community of Weed Heights, purchased by Don Tibbals of Tibbals Construction (December 29, 1982).

1983  NDEP personnel and Lyon County Commissioners met to discuss the investigation of groundwater and surface water contamination.

1985 Under an Administrative Order issued by NDEP, ARC constructed the pumpback well system, including five pumpback wells (PW-1 through PW-5) and the associated approximate 23-acre pumpback evaporation pond.

1986 Copper Tek leaching operations were shut down by NDEP. An FOV and Administrative Order were issued to Tibbals in December.

1989 Don Tibbals and Copper Tek sold the Site to Arimetco, effective August 7, 1989, with the exception of the community of Weed Heights and a portion of the oxide tailings area. Copper Tek continued to operate the Yerington Project as an operating subsidiary of Arimetco.

1989  Arimetco began heap leaching and processing operations.

1990  The U.S. Environmental Protection Agency (EPA) conducted a Comprehensive Environmental Response, Compensation, and Liability Act of 1980 (CERCLA) evaluation of the Site.

1991  Unison ended lease agreement and ceased transformer dismantling operations at the former Yerington Mine Site.

1992  Canonie Environmental signed a contract with Arimetco No. 84112-01.001 on June 26 to continue operations and maintenance of the pumpback well system and evaporation ponds, monthly water monitoring, and semiannual water quality sampling.

1993  Arimetco expanded onsite operations and posts a reclamation bond/corporate guarantee totaling $3.5 million as part of its financial assurance for reclamation.

1994  EPA conducted CERCLA prioritization and determined that the Anaconda Copper Mine was eligible for listing on the National Priorities List (NPL) as a Superfund site.

1997  Arimetco filed for bankruptcy protection but continued to operate the mine until January 2000.

1998  The U.S. Bureau of Land Management (BLM) was notified of NDEP concerns of offsite contamination, and NDEP requested BLM to consider the Site as a potential threat to groundwater and expedite steps for remediation.

1998 ARC installed six additional pumpback wells (PW-6 through PW-11) and modified the evaporation pond by partitioning the pond into three cells and adding clay liners.

1998  On December 17, NDEP issued Arimetco a Notice of Noncompliance and Order requiring them to reduce levels of operation down to a care and maintenance level and cease adding new ore and makeup water to the heap leach pads.

1999  ARC completed construction of the upgrades to the pumpback system. The system consists of six pumpback wells, one new monitoring well, and an evaporation pond divided into three cells.

2000  Arimetco abandoned operations at the Site, leaving four operational heap leach pads (HLP) with approximately 90 million gallons of pregnant leach solution (PLS) still in the system. The Site comes under NDEP Emergency Management.

2000 In September, NDEP capped a partially excavated, planned Arimetco Fluids Pond, north of the vat leach tailings (VLT) HLP, with VLT material, to mitigate ““red dust”” exposed during early construction. The newly scoped VLT pond was not completed.

2000 In October, EPA conducted an expanded Site Inspection, which included collecting groundwater samples from monitoring wells on and around the Site and standing water from a belowground cellar, PLS, tailings, and leachate salts.

2000 ARC upgraded the liner systems in the middle and south Pumpback Well System (PWS) evaporation ponds by installing 60-mil high-density polyethylene (HDPE) over the top of the existing clay liners. The north cell remains lined with the clay liner installed in 1998.

2000  In December, EPA requested Nevada’’s position on listing the Site on the NPL.

2001  In January, Nevada responded to EPA’’s letter regarding NPL listing and did not support listing.

2001  In March, NDEP capped three areas with VLT material, including (1) an area of calcines that were removed from the solution storage tanks and placed on top of the oxide tailings, (2) areas within the former calcine ditch, and (3) one of the strong fluids storage tanks to mitigate fugitive ““red dust”” generated on the Site.

2002  In March, NDEP completed capping of the Thumb Pond (the largest of the finger ponds) with VLT material to mitigate ““red dust.””

2002 On March 28, a Memorandum of Understanding (MOU) was signed between NDEP, EPA, and BLM regarding coordination and oversight of assessment, characterization, and response activities at the Site. NDEP will coordinate all work to be performed under the October 24 Administrative Order on Consent, consistent with the requirements of the MOU. As parties to the MOU, BLM, and EPA will participate in the review of activities and requirements under this order.

2002  On September 23, NDEP issued an alleged FOV and order to Arimetco requiring that it generate a work plan and schedule for removing and disposing of remaining materials onsite. On October 23, NDEP issued a notice of the failure to comply and took over removal actions.

2003  In January, as part of the Site cleanup and removal action, NDEP arranged for collection and analysis of 400 drums and fluids remaining in the Arimetco solvent extraction (SX) and electrowinning (EW) facilities. The drum and EW removal projects were funded by the State of Nevada, were conducted through SRK Consulting, and have since been reimbursed by ARC.

2004  EPA assumed regulatory control of the Site.

2005  In March, EPA issued ARC a Unilateral Administrative Order Docket No. 9-2005-0011 to continue initial response actions.

2005 In October, EPA personnel conducted a removal assessment to determine issues that should be addressed short term. EPA determined two necessary activities: (1) ridding the Site of polychlorinated biphenyls (PCB) and (2) controlling mine waste containing dust from blowing off the Site.

2006 EPA removed approximately 170 transformers, switches, and containers at the Site that potentially contained unacceptable levels of PCBs.

2006 Using VLT material, EPA capped portions of the sulfide tailings area not previously capped and applied a sealant to other areas on the Site that were determined to be contributing to fugitive dust emissions.

2006  EPA constructed a 4-acre evaporation pond to contain excess drain-down fluids from the Arimetco heap leach fluids management system.

2007  In January, EPA issued ARC a Unilateral Administrative Order Docket
No. 9-2007-0005 to begin the Site wide remedial investigation and feasibility study process.

2007  EPA conducted a removal action to address fluid management issues associated with the Bathtub Pond. Removal actions included removing sediments and liner from the pond, backfilling and grading the pond, and constructing an interceptor trench along the shoulder of the pond.

2008  EPA removed the Mega Pond, two Raffinate Ponds, and the PLS Pond. Removal actions included removing sediments and liner from the ponds and backfilling and grading the ponds.

2008 EPA removed two organic traps (Vaults A and B), excavated kerosene-contaminated soils, and constructed the bioremediation cells on top of the Phase IV Slot HLPs.

2008  EPA approved a minimum 1-year shutdown of the PWS to evaluate its effectiveness and to investigate the shallow and intermediate hydraulic zones underlying northern areas of the Site.

2009  EPA issued ARC an Administrative Order on Consent Docket No. 09-2009-0010 for removal actions and settlement on past EPA response costs.

2010  EPA performed several removal actions, including removing the former Mine Site Administrative Building with asbestos-containing material, removing the tire pile located east of the Process Area, and improving existing security perimeter fencing.

2010 PA completed a Draft Supplemental Remedial Investigation and Human Health Risk Assessment on the Arimetco HLPs and Fluids.

Source: 

“Historical Summary Report Anaconda-Yerington Mine Site Yerington, Nevada”

Prepared for:
Contract No. EP-S9-08-04/Task Order No. 012-RSBD-09GU U.S. Environmental Protection Agency
Region 9
75 Hawthorne Street
San Francisco, California 94105

Prepared by:
CH2M HILL, Inc.
50 West Liberty Street, Suite 205 Reno, Nevada 89501

October 2010